New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 106 Topic 11 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 106 Topic 11 Discussion

PMP Exam Topic 11 Question 106 Discussion:
Question #: 106
Topic #: 11

A team is delivering features to a customer at every iteration. After completing each iteration, the customer is invited for a review. However, the customer is frequently not

available and the review is often delayed, which results in increased rework for the team.

What should the project manager do?


A.

Ask the customer to review the deliverables in each iteration based on their availability.


B.

Request the customer to clarify all requirements at the start of each iteration.


C.

Plan ahead and define the best way to review the deliverables with the customer.


D.

Include the customer in daily project activities to gain the required guidance.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.