Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 228 Topic 23 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 228 Topic 23 Discussion

PMP Exam Topic 23 Question 228 Discussion:
Question #: 228
Topic #: 23

A customer complains that the user stories released so far contain too much jargon and do not reflect the expectations of the product. What should the project manager do

next?


A.

Request approval from the company director to conduct training for the team.


B.

Ask the senior developer to rewrite all the stories.


C.

Engage with the customer and rewrite all the stories.


D.

Rewrite the stories to include the technical vision of the product.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.