PMI Project Management Professional (2025 Version) PMP Question # 117 Topic 12 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 117 Topic 12 Discussion

PMP Exam Topic 12 Question 117 Discussion:
Question #: 117
Topic #: 12

A project team has recently completed the initial sprint for developing an automated payroll system for a company The project manager has scheduled a sprint planning meeting with the product owner and team members to discuss which features should be worked on next

Which two pieces of information does the project manager need in order to make this meeting productive and effective? (Choose two)


A.

Sprint charter


B.

Burndown chart


C.

Company mission and vision


D.

Product backlog


E.

Sprint goal


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.