An agile team has completed 9 out of 10 stones tor the sprint. During the retrospective a few team members pointed out that they finished a of their stories However one team member tailed to finish a story
What should the agile leader do1?
A.
Emphasize to the team that each member is responsible for their story but the team is collectively responsible for finishing the sprint
B.
Ask the team to address this at the next sprint planning instead of at the retrospective
C.
Suggest that the team assign stones at the beginning of the sprint based on each person's strengths to maximize performance
D.
Work with the product owner to remove the story from the sprint because the points cannot be splits
In Agile methodologies, it’s important to remember that while each team member may work on specific tasks or “stories,” the team as a whole is responsible for the completion of the sprint. This means that if one story is not completed, it’s a reflection on the team, not just the individual who was working on that story. The Agile leader should emphasize this collective responsibility and encourage team members to help each other in order to ensure the completion of all stories in future sprints. References: PMBOK Guide, 6th Edition, Section 9.3.3.3: Team Performance Assessments. Agile Practice Guide, Section 2.3: Team Roles.
Contribute your Thoughts:
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.
Submit