PMI Project Management Professional (2025 Version) PMP Question # 117 Topic 12 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 117 Topic 12 Discussion

PMP Exam Topic 12 Question 117 Discussion:
Question #: 117
Topic #: 12

A project is nearing the completion of a sprint when the product owner announces that a local regulator has banned part of the deliverable. What should the project manager do?


A.

Add more items to the sprint backlog that will add value.


B.

Complete the sprint and seek a waiver from the regulator.


C.

Complete the sprint, but do not release the deliverable.


D.

Perform a sprint risk assessment and analyze challenges.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.