New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 117 Topic 12 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 117 Topic 12 Discussion

PMP Exam Topic 12 Question 117 Discussion:
Question #: 117
Topic #: 12

An agile project is running its third iteration with a duration of 2 weeks. A new operations director, who only has a predictive background, started

working at the company. In the first meeting with the project manager, the director demands a weekly project status report.

What should the project manager do?


A.

Invite the director to attend the daily standup meetings.


B.

Share this with the team and ask them to develop reports for the director.


C.

Introduce the agile aspect to the director and agree on a solution.


D.

Explain to the director that agile projects have live reports.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.