Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 117 Topic 12 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 117 Topic 12 Discussion

PMP Exam Topic 12 Question 117 Discussion:
Question #: 117
Topic #: 12

An agile team has completed 9 out of 10 stones tor the sprint. During the retrospective a few team members pointed out that they finished a of their stories However one team member tailed to finish a story

What should the agile leader do1?


A.

Emphasize to the team that each member is responsible for their story but the team is collectively responsible for finishing the sprint


B.

Ask the team to address this at the next sprint planning instead of at the retrospective


C.

Suggest that the team assign stones at the beginning of the sprint based on each person's strengths to maximize performance


D.

Work with the product owner to remove the story from the sprint because the points cannot be splits


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.