PMI Project Management Professional (2025 Version) PMP Question # 362 Topic 37 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 362 Topic 37 Discussion

PMP Exam Topic 37 Question 362 Discussion:
Question #: 362
Topic #: 37

A project manager for a software development company faces a number of financial risks in their project. The project manager needs to frequently check the strength and

efficiency of the risk management process.

What should the project manager use to accomplish this?


A.

Stakeholder register


B.

Brainstorming session


C.

Audit meeting


D.

Assumption log


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.