Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 254 Topic 26 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 254 Topic 26 Discussion

PMP Exam Topic 26 Question 254 Discussion:
Question #: 254
Topic #: 26

A scrum team's daily meetings are conducted by teleconference between three teams, each located in different countries. The meetings typically

last 45 minutes with many misunderstandings due to language barriers.

How should the project manager resolve this issue for the next iteration?


A.

Transfer half of the backlog items to the next iteration to allow more time to complete the meetings.


B.

Extend the meeting to 1 hour and request that all of the participants bring up all of the issues.


C.

Instruct the meeting participants to speak only about blockers during the meeting.


D.

Train the three team leads to conduct a local meeting, then run an overall status meeting.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.