PMI Project Management Professional (2025 Version) PMP Question # 96 Topic 10 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 96 Topic 10 Discussion

PMP Exam Topic 10 Question 96 Discussion:
Question #: 96
Topic #: 10

An organization is embarking on the deployment of a new digital solution that will revolutionize purchasing services The project manager has created all the necessary plans and activities to ensure a successful integration and solution launch There is a risk of a partner’s system being unavailable which could impact the project negatively

What key activity is needed to ensure the project's success?


A.

Communicate to the project stakeholders that full integration may not be possible and that the project will potentially be delayed as a result.


B.

Eliminate the risk by mandating the partner to change the system settings to facilitate an easier integration with the new solution


C.

Continuously monitor the risk of the partner system's unavailability, and put the proper resolution plans in place in case the risk materializes into an actual issue


D.

Mitigate the risk by developing alternative plans to make the solution ready and available without full integration capabilities


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.