PMI Project Management Professional (2025 Version) PMP Question # 96 Topic 10 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 96 Topic 10 Discussion

PMP Exam Topic 10 Question 96 Discussion:
Question #: 96
Topic #: 10

A project is in the execution phase and there are disagreements between two key stakeholders about the project's scope. One stakeholder is adamant about expanding the scope and the other stakeholder is content with the current arrangement.

What should the project manager do?


A.

Escalate the stakeholder's conflict to senior management so they can resolve the issue.


B.

Schedule a one-on-one discussion with each stakeholder to understand their concerns.


C.

Schedule a meeting with both stakeholders to encourage dialogue and reach a decision.


D.

Suggest that the two stakeholders meet together to agree upon a project scope.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.