New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 96 Topic 10 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 96 Topic 10 Discussion

PMP Exam Topic 10 Question 96 Discussion:
Question #: 96
Topic #: 10

A large construction project is progressing well as per the project objectives. The project manager would like to report the project's value to the project sponsor and seek the

next phase of funding closure.

What should the project manager do?


A.

Ensure a measurement system is in place like earned value analysis (EVA) to track project value for the project sponsor.


B.

Submit a detailed report on the cost budget vs. the cost actuals as the project sponsor will want to know more about finances.


C.

Create a detailed project report on successes and challenges for the project sponsor.


D.

Arrange a site visit to show the project sponsor the construction progress in person.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.