PMI Project Management Professional (2025 Version) PMP Question # 99 Topic 10 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 99 Topic 10 Discussion

PMP Exam Topic 10 Question 99 Discussion:
Question #: 99
Topic #: 10

A project manager was assigned to lead a global project with a virtual team that is globally dispersed. The project manager has difficulties communicating with the team members and there seems to be frequent misunderstandings and conflicts.

What should the project manager do?


A.

Ask the team members to refamiliarize themselves with the communications management plan.


B.

Organize effective communication training for team members.


C.

Listen to team members actively and change the communication practices accordingly.


D.

Model servant leadership by adapting to team requirements.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.