PMI Project Management Professional (2025 Version) PMP Question # 99 Topic 10 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 99 Topic 10 Discussion

PMP Exam Topic 10 Question 99 Discussion:
Question #: 99
Topic #: 10

As part of the strategic plan, a company decides to implement a new software platform to manage a centralized document repository. Some requirements are clear and some need more detail.

What should the project manager do first to decide how to manage this project?


A.

Select a predictive development life cycle based on the team's experience


B.

Determine the most appropriate life cycle approach for the project


C.

Register all requirements into a backlog for further detailed analysis.


D.

Split the requirements, put them into two separate projects, and apply different approaches


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.