Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 100 Topic 11 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 100 Topic 11 Discussion

PMP Exam Topic 11 Question 100 Discussion:
Question #: 100
Topic #: 11

A project manager is leading a project to modemize the information technology of a bank. The project manager needs to determine how the project stakeholders should communicate, and has discussed the various options with the project team.

What should the project manager do to communicate with the stakeholders?


A.

Provide updates to the project sponsor to review and distribute to each stakeholder.


B.

Use a single communication medium such as video teleconferencing to limit confusion.


C.

Use a variety of communication methods that respect cultural, practical, and personal preferences.


D.

Send frequent updates via email to each stakeholder because this is an information technology project.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.