PMI Project Management Professional (2025 Version) PMP Question # 100 Topic 11 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 100 Topic 11 Discussion

PMP Exam Topic 11 Question 100 Discussion:
Question #: 100
Topic #: 11

A project team member who was a top performer in the planning phase of a project was easily irritated during the fifth sprint of the software development phase. The team member's attitude and behavior made the other team members feel uncomfortable.

What should the project manager do?


A.

Assess the workload of each team member and redistribute tasks.


B.

Meet with the team member to offer any help that may be needed.


C.

Reorganize the team to reduce the interactions causing the team discord.


D.

Arrange an immediate agile training course for the team member.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.