New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 100 Topic 11 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 100 Topic 11 Discussion

PMP Exam Topic 11 Question 100 Discussion:
Question #: 100
Topic #: 11

A project manager works for an organization that intends to begin using agile delivery, but there is a lack of support from some business units. The project manager needs to address the lack of trust in agile.

What should the project manager recommend?


A.

Implement and establish an agile framework for the project.


B.

Hire a team of contractors for agile project delivery.


C.

Define detailed work instructions for agile project delivery.


D.

Negotiate special arrangements for an agile pilot project.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.