PMI Project Management Professional (2025 Version) PMP Question # 66 Topic 7 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 66 Topic 7 Discussion

PMP Exam Topic 7 Question 66 Discussion:
Question #: 66
Topic #: 7

A town wants to build a community center and has appointed a project manager. A site was found, and all of the necessary approvals and governance were completed. When the project kick-off was held, it was discovered that a local farmers' group was not consulted, and they use the site for a monthly market.

What should the project manager do to move forward with the project?


A.

Continue building the center as the farmers' group does not need to be consulted.


B.

Document a risk related to the impact that the farmers' group could bring to the project.


C.

Request that the project sponsor discuss compensation with the farmers' group for the lost business.


D.

Discuss the project objectives with all stakeholders, including the farmers' group, and review their requirements.