Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 66 Topic 7 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 66 Topic 7 Discussion

PMP Exam Topic 7 Question 66 Discussion:
Question #: 66
Topic #: 7

A protect team is working remotely on a solution The client wants the solution as soon as possible and is uncomfortable because the team members are not colocated In addition the client expressed concerns about the understanding of the project context and the team's decision-making process

What should the project manager do?


A.

Update the communications management plan to satisfy the client's request


B.

Request the client to attend the daily meetings with the project team


C.

Encourage the client to interact with the protect collaboration platform


D.

Ask the product owner to frequently communicate with the stakeholders


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.