PMI Project Management Professional (2025 Version) PMP Question # 64 Topic 7 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 64 Topic 7 Discussion

PMP Exam Topic 7 Question 64 Discussion:
Question #: 64
Topic #: 7

A project manager just took over a construction project which was already in its execution phase. Labor union representatives of the construction workers ask to revise the overtime per hour rate, as wage per hour have increased across the industry.

What should the project manager do first?


A.

Obtain approval from sponsors to increase the rates because it can affect project due to lack of resources.


B.

Carefully read the agreements and see if there was any clause if the per hour rate could be increased.


C.

Assign a team member to negotiate the increased wage per hour with the labor union representatives.


D.

Negotiate with the labor union representatives if the clause about increased wage per hour meets their requirements.