Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 212 Topic 22 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 212 Topic 22 Discussion

PMP Exam Topic 22 Question 212 Discussion:
Question #: 212
Topic #: 22

During the project planning phase, a project manager is informed that they cannot start one activity before another department implements the

required IT system. What should the project manager do?


A.

Fast track this dependency to avoid delaying the project.


B.

Perform Integrated Change Control.


C.

Include the dependency in the project schedule.


D.

Ask IT to prioritize the needed system to meet the schedule.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.