PMI Project Management Professional (2025 Version) PMP Question # 207 Topic 21 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 207 Topic 21 Discussion

PMP Exam Topic 21 Question 207 Discussion:
Question #: 207
Topic #: 21

A project manager is leading a cross-organizational project that is replacing a platform on which various solutions used by 15 business units were built. The project is part of a large program of work, and some of the resources are shared with other projects outside of the program initiated by the respective business units.

Which stakeholders should the project manager consult with first to manage interdependencies?


A.

Project sponsors


B.

Other project managers


C.

Business unit managers


D.

Program managers