PMI Project Management Professional (2025 Version) PMP Question # 207 Topic 21 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 207 Topic 21 Discussion

PMP Exam Topic 21 Question 207 Discussion:
Question #: 207
Topic #: 21

A project manager is managing a project which is approaching the end of the execution phase. A high-level stakeholder informs the project manager that a very important requirement was not included in the scope of the project, and that without that requirement the project will deliver no value.

What is the first thing the project manager should do"?


A.

Include the requirement into the project and schedule it as soon as possible


B.

Inform the project sponsor about the situation and request assistance


C.

Evaluate the impact that the inclusion of this new requirement will have on project performance


D.

Inform the stakeholder that it is impossible to add new requirements to an approved project scope


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.