A project is experiencing delays due to identified risks What should the project manager do to manage the project schedule?


A.

Revise the project schedule and inform the stakeholders regarding any delays


B.

Revise the project estimates and meet with the project team to discuss delays


C.

Review the management reserve to identify any costs associated with the delays


D.

Review the contingency reserve to identify any delays to the project