New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 61 Topic 7 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 61 Topic 7 Discussion

PMP Exam Topic 7 Question 61 Discussion:
Question #: 61
Topic #: 7

A project is approaching the closing phase. While preparing for the final steps, the quality system is updated in accordance with new international quality standards, resulting in new deliverable/approval procedures.

Which action should the project manager take?


A.

Apply the new list of approval procedures.


B.

Escalate the issue to the project sponsor.


C.

Ask the project team if the scope can be changed.


D.

Inform the customer that the project will be late.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.