PMI Project Management Professional (2025 Version) PMP Question # 56 Topic 6 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 56 Topic 6 Discussion

PMP Exam Topic 6 Question 56 Discussion:
Question #: 56
Topic #: 6

A project manager is leading a team and wants each team member to produce their deliverables and be held accountable for the work product. What should the project manager do first?


A.

Engage with each project team member to explain the individual consequences of late delivery.


B.

Establish a daily standup meeting where each project team member reports their progress.


C.

Create a plan of action and milestones (POAM) to detail the deliverables for each project team member.


D.

Empower each project team member with ownership of a particular aspect of the project.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.