Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Project Management Professional (PMP) July 2026 Update PMP Question # 56 Topic 6 Discussion

PMI Project Management Professional (PMP) July 2026 Update PMP Question # 56 Topic 6 Discussion

PMP Exam Topic 6 Question 56 Discussion:
Question #: 56
Topic #: 6

A project team is equipping a small hospital. To complete the work, the team requires an additional service provided by an external supplier. The price quoted by the

supplier is surprisingly high, which may cause a significant increase in the budget.

What should the project manager do?


A.

Utilize the contingency reserve to manage the procurement.


B.

Discuss using the management reserve with the sponsor.


C.

Ask the procurement manager to find another supplier.


D.

Request the supplier fulfil their obligations by adjusting costs.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.