Question #: 78
Topic #: 8

A company routinely outsources resources for specific core activities. Due to a sudden, unforeseen risk, all of the team members are needed to work remotely, including the outsourced ones.

How can the project manager address this challenge to assure outsourced vendors deliver?


A.

Review the coordination and communication costs with the supplier.


B.

Develop a new strategy for communication and management of resources.


C.

Review the risk management plan for the mitigation activities.


D.

Submit a change request to increase the contingency budget.