Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 178 Topic 18 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 178 Topic 18 Discussion

PMP Exam Topic 18 Question 178 Discussion:
Question #: 178
Topic #: 18

A project manager has been assigned to a new project that will be delivered using an agile framework. The sponsor is asking for a cost estimation to build the business case.

What should the project manager do?


A.

Ensure the client representative is involved in the estimation.


B.

Review the completion costs of similar projects.


C.

Ensure that a 20% contingency is included in the estimation.


D.

Review the lessons learned from similar projects.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.