PMI Project Management Professional (2025 Version) PMP Question # 184 Topic 19 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 184 Topic 19 Discussion

PMP Exam Topic 19 Question 184 Discussion:
Question #: 184
Topic #: 19

An organization uses a hybrid approach to project management. A project manager has been assigned to an external project, project A, where two of the three modules in the project require machine learning skills. The only machine learning expert in the project manager's organization is engaged in an internal project, project B, that is about to end.

What should the project manager do?


A.

Prioritize project A over project B since A is an external project and B is an internal project.


B.

Plan projectA in sprints, starting with the module that does not require machine learning skills.


C.

Engage the human resource manager to employ a machine learning expert for project A.


D.

Plan project A to start at the end of project B when the machine learning expert is available.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.