Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 343 Topic 35 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 343 Topic 35 Discussion

PMP Exam Topic 35 Question 343 Discussion:
Question #: 343
Topic #: 35

A project manager is struggling to provide timely updates to the project team due to team members being spread across multiple time zones. Which communications method should the project manager utilize in this situation?


A.

Interactive communication


B.

Public communication


C.

Pull communication


D.

Push communication


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.