Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 343 Topic 35 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 343 Topic 35 Discussion

PMP Exam Topic 35 Question 343 Discussion:
Question #: 343
Topic #: 35

A project manager is leading a project which shows a trend to exceed the cost baseline What should the project manager do first to manage the budget?


A.

Ask the project sponsor for assistance in getting the budget back on track


B.

Meet with the project team to analyze the actual cost to determine deviations


C.

Inform the stakeholders that the project will be finished over budget.


D.

Issue a change request including the analysis to increase the budget


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.