PMI Project Management Professional (2025 Version) PMP Question # 343 Topic 35 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 343 Topic 35 Discussion

PMP Exam Topic 35 Question 343 Discussion:
Question #: 343
Topic #: 35

A hybrid project has just deployed, and the project manager is planning project closure with lessons learned workshops. A key stakeholder informs the project manager that having the Scrum team in the workshops is a waste of time because the project was delivered successfully.

What should the project manager do?


A.

Ask the Scrum team members to share retrospectives.


B.

Ask the scrum master to attend the workshops.


C.

Invite the Scrum team members as optional participants.


D.

Invite the Scrum team members as mandatory participants.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.