Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 342 Topic 35 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 342 Topic 35 Discussion

PMP Exam Topic 35 Question 342 Discussion:
Question #: 342
Topic #: 35

A company is changing their current business model The change requires implementing a complex project using multiple agile teams.

What three options should the project manager have the testing team adopt as testing mechanisms? (Choose three)


A.

Independent personal testing


B.

Security and performance testing


C.

An experimental approach to cover all possible choices


D.

Story testing


E.

Tests based on behavior and test-driven development


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.