Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 341 Topic 35 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 341 Topic 35 Discussion

PMP Exam Topic 35 Question 341 Discussion:
Question #: 341
Topic #: 35

A project manager recently took over an ongoing project. Within a few weeks on the project, the project manager discovers that there are continuous change requests from different project end users. What is the probable cause for this?


A.

Undefined change control process


B.

Unidentified project risks


C.

Improper work breakdown structure (WBS)


D.

Incomplete requirements


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.