Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 341 Topic 35 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 341 Topic 35 Discussion

PMP Exam Topic 35 Question 341 Discussion:
Question #: 341
Topic #: 35

The following table shows the business value created and the development effort required to implement various features in a product

PMP Question 341

Which feature should the team prioritize first? Enter the feature name in the box below

PMP Question 341


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.