Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 336 Topic 34 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 336 Topic 34 Discussion

PMP Exam Topic 34 Question 336 Discussion:
Question #: 336
Topic #: 34

A project manager is leading a project at a contracting company, and the project

team just completed an iteration. The product passed inspection, but an additional feature was added to the product. The customer notices the additional feature and thinks it will introduce new risks to the product.

What should the project manager do to avoid this situation in the future?


A.

Manage the scope baseline to influence the factors that drive change.


B.

Follow the proper change control process and evaluate the change for further impact.


C.

Work with the customer to ensure the feature adds value.


D.

Perform frequent reviews with the customer to ensure that the product is working asexpected.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.