New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 420 Topic 43 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 420 Topic 43 Discussion

PMP Exam Topic 43 Question 420 Discussion:
Question #: 420
Topic #: 43

A project manager has been assigned to an education project with the objective of training a workforce in application development One of the deliverables is to provide internships to the best students in the customer's active projects However the customer does not have enough projects in progress right now The project manager decides to create several internal projects in order to ensure the internships

Which three actions should the project manager take to fulfill this scenario without adding costs for the customer? (Choose three)


A.

Use the project's contingency budget


B.

Create a change request with the scope of the new internal projects.


C.

Influence the client to initiate a new project.


D.

Create a work breakdown structure (WBS) of the new scope with the internal projects


E.

Manage the quality of the delivery


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.