PMP Exam Topic 43 Question 420 Discussion:
Question #: 420
Topic #: 43

Stakeholders in some industries prefer to deal with programmers and system analysts directly, bypassing project managers. This complicates managing resources on projects

How should a project manager solve this issue?


A.

Propose implementing a new project management information system (PMIS).


B.

Request a meeting with senior management to escalate the situation


C.

Promote adoption of the communications management plan with the project team.


D.

Host a team-building event to develop team cohesion and improve communication