Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 448 Topic 45 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 448 Topic 45 Discussion

PMP Exam Topic 45 Question 448 Discussion:
Question #: 448
Topic #: 45

An organization is introducing agile to its projects. During an informal discussion the project manager learned that team members who are currently working on different teams are discussing how they would like to be together on the same team

What should the project manager do?


A.

The project manager should not allow resources to choose teams because the project manager assigns the resources based upon project needs


B.

The project manager should not allow resources to choose on which team they would like to work because they will always choose their favorite team


C.

The project manager should allow the resources to periodically choose on which team they would like to work.


D.

The project manager should indicate that the team members have already been assigned to a team through workforce optimization


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.