PMI Project Management Professional (2025 Version) PMP Question # 428 Topic 43 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 428 Topic 43 Discussion

PMP Exam Topic 43 Question 428 Discussion:
Question #: 428
Topic #: 43

During project execution, one of the project tasks is to create an important document for a service vendor. The project manager assigns a senior engineer to clearly detail

the service instructions to avoid any redo loops. Two days after the service information document was sent, the service vendor has doubts and needs more clarity on the task. This redo loop will probably cause a delay of one or more days.

What should the project manager do next?


A.

Escalate the issue to the engineer's functional manager.


B.

Discuss the issue with the engineer and determine how to prevent another problem.


C.

Document the task on the kanban board and make it the highest priority.


D.

Assign another engineer to the task due to the urgency.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.