Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 406 Topic 41 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 406 Topic 41 Discussion

PMP Exam Topic 41 Question 406 Discussion:
Question #: 406
Topic #: 41

Some members of a project team are frustrated by a new team member who previously worked in a Scrum setting This new team member approaches members of the project team on a daily basis in what appears to be an attempt to engage in individual standup meetings

What should the project manager do?


A.

Schedule a meeting for the project team to review the communications management plan.


B.

Tell the rest of the project team to continue discussions with the new team member


C.

Send an email to the project team outlining the communications strategy.


D.

Mentor the new team member on the methodology the project team is using


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.