PMI Project Management Professional (2025 Version) PMP Question # 406 Topic 41 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 406 Topic 41 Discussion

PMP Exam Topic 41 Question 406 Discussion:
Question #: 406
Topic #: 41

A project manager is reviewing the status of a large project with team members in different countries. Through the status review, the project

manager notices that one team is consistently behind schedule and their work often needs to be corrected.

What should the project manager do to improve the quality of this team's work?


A.

Evaluate the issue with the team to determine if they have the necessary skills to perform assignments.


B.

Review the issue with the project sponsor and work to reduce the scope for that team.


C.

Guide all team members and bring in external consultants to complete the work.


D.

Ask a local subject matter expert (SME) to assist the team in reviewing the project requirements.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.