Question #: 427
Topic #: 43

During the development phase, a team member encounters an issue with a specific task and attempts to resolve it for the next several days. The other team members ask

the project manager to reassign the task to another team member to avoid jeopardizing the target date. The current team member assigned communicates they will feel frustrated if the task is reassigned to another team member.

How should the project manager address this situation?


A.

Seek help from experts to support the team member in fixing the problem.


B.

Facilitate a session to reach an agreement with the team as a whole.


C.

Negotiate with the customer a delay in the project delivery.


D.

Accept the team's request to reassign the team member.