Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 425 Topic 43 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 425 Topic 43 Discussion

PMP Exam Topic 43 Question 425 Discussion:
Question #: 425
Topic #: 43

A large project is affecting the neighborhood in which it is located The neighbors are not satisfied with the project and their resistance to the project may affect the project deadline

What two actions should the project manager take'? (Choose two)


A.

Send letters to the neighbors and ask them kindly not to disturb the project.


B.

Set up a meeting with neighborhood representatives to win their cooperation


C.

Analyze the situation and find out what is causing the neighborhood's negative attitude.


D.

Ask the customer to extend the project deadline to allow time for conflict resolution


E.

Ask the mayor of the city to use their authority to stop neighborhood resistance


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.