Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 241 Topic 25 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 241 Topic 25 Discussion

PMP Exam Topic 25 Question 241 Discussion:
Question #: 241
Topic #: 25

A company's project management office (PMO) has started to implement iterative tools. The project manager is starting a new project and has

identified an opportunity to use the new tools. There is disagreement among stakeholders about the use of the adaptive tool.

What should the project manager do first?


A.

Investigate the reasons for the disagreement to understand the gap among the stakeholders and search for consensus.


B.

Discuss the situation with the stakeholders to evaluate other adaptive tools for the project.


C.

Schedule training sessions for the stakeholders on the benefits of the adaptive tools.


D.

Update the risk register and escalate the disagreement to the project sponsor and distribute the status to the team.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.