PMP Exam Topic 24 Question 234 Discussion:
Question #: 234
Topic #: 24

A project manager is assigned to an agile project that has an aggressive time line and a fixed budget. Currently, the majority of the items are in the backlog and only a few are in process or completed.

What should the project manager do?


A.

Prioritize which backlog activities should be kept.


B.

Work on the backlog activities with fewer story points.


C.

Ask for more resources to clear the backlog activities.


D.

Assign an owner for each backlog activity and track progress.