Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 225 Topic 23 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 225 Topic 23 Discussion

PMP Exam Topic 23 Question 225 Discussion:
Question #: 225
Topic #: 23

An iteration is almost finished, but the team is struggling to complete the stories that require more time. What should the project manager do first?


A.

Meet with the project team to develop a proper resolution to the issue.


B.

Update the project artifacts to reflect the new deadlines reported.


C.

Request approval from the project sponsor to add more resources,


D.

Prepare documentation to explain the issue and communicate accordingly.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.