Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 233 Topic 24 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 233 Topic 24 Discussion

PMP Exam Topic 24 Question 233 Discussion:
Question #: 233
Topic #: 24

A project manager has recently moved to an organization to lead a key project. The project manager notices that team performance is below the target, and the tasks assigned are not delivered on time. Team commitment is also not as appropriate as it should be.

What should the project manager do?


A.

Study and determine the appropriate leadership style suitable for the team.


B.

Hire a project team leader who can influence the project team members.


C.

Schedule a meeting and communicate the performance concern to the team.


D.

Apply an agile approach to help improve team performance.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.