Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 210 Topic 22 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 210 Topic 22 Discussion

PMP Exam Topic 22 Question 210 Discussion:
Question #: 210
Topic #: 22

A proof of concept for a proposed solution was conducted during the project implementation, and it was determined that the current technology cannot support it. What should the project manager do next?


A.

Ask another team member to redo the proof of concept using the current technology to ensure It is truly not an option.


B.

Use a root cause analysis (RCA) technique like Ishikawa diagrams to determine why the current technology is not supportive.


C.

Add this item to the issue log and explore possible resolution options with the team.


D.

Update the risk register indicating that a new technology must be chosen by the team lead.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.