PMI Project Management Professional (2025 Version) PMP Question # 210 Topic 22 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 210 Topic 22 Discussion

PMP Exam Topic 22 Question 210 Discussion:
Question #: 210
Topic #: 22

Due to organizational changes: several key stakeholders are replaced by new ones in the middle of a project. As a result, numerous new requirements are raised What should the project manager do to ensure success of the project?


A.

Review and prioritize new requirements with stakeholders to determine which change requests are needed.


B.

Escalate the issue to the project sponsor and seek support to keep the original requirements.


C.

Seek immediate approval to amend the project timeline and budget in order to deliver all new requirements


D.

Emphasize to the new stakeholders that new requirements are not allowed at this stage of the project


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.