A project is on its second iteration out of six. The team realizes that a key deliverable will depend on the acquisition of a new device.

What should the project manager do?


A.

Register a risk and escalate it to the project sponsor.


B.

Include the responsibility for acquisition with the core team.


C.

Detail the reason for the deliverable delay in the status report.


D.

Invite the stakeholders to discuss prioritization of a new deliverable.