Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Project Management Professional (PMP) July 2026 Update PMP Question # 42 Topic 5 Discussion

PMI Project Management Professional (PMP) July 2026 Update PMP Question # 42 Topic 5 Discussion

PMP Exam Topic 5 Question 42 Discussion:
Question #: 42
Topic #: 5

A project to launch a new financial product is on its fifth out of eight iterations. During the iteration review, a financial stakeholder announces a competitor is launching

a similar product soon. As a result, the stakeholder asks the team to increase velocity.

What should the project manager do?


A.

Ask for additional resources to finish the project sooner.


B.

Meet with the key stakeholders to discuss prioritization.


C.

Update the risk log and define a contingency plan.


D.

Ask the team to present a proposal to the requesting stakeholder.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.