PMI Project Management Professional (2025 Version) PMP Question # 42 Topic 5 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 42 Topic 5 Discussion

PMP Exam Topic 5 Question 42 Discussion:
Question #: 42
Topic #: 5

A project manager's project relies on services from a department that has a new leader. Since the new leader was appointed, the services from their department have been slow which threatens the project's delivery deadline.

What should the project manager do?


A.

Add the issue to the issue log and communicate the issue in the next regular report to project stakeholders.


B.

Escalate the issue to the project sponsor notifying them of the slow services from the department.


C.

Send all service requests to the department earlier in the project to lessen the impact on the delivery date.


D.

Arrange a meeting with the leader to explain the project's needs and understand the leader's perspective.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.