PMI Project Management Professional (2025 Version) PMP Question # 44 Topic 5 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 44 Topic 5 Discussion

PMP Exam Topic 5 Question 44 Discussion:
Question #: 44
Topic #: 5

A company has rolled out the latest retail management system, and the project has been handed over to operations. The operations team finds that many of the day-to-day requirements are not covered in the system, and support for the project has limited hours, The project team has dissolved and the contract resources are no longer working on the project. As a result, the operations team has been facing numerous customer issues.

What should the project lead have done initially to avoid this situation?


A.

Reviewed the project management plan


B.

Created a detailed operations manual


C.

Increased support hours for the hours of operation


D.

Involved operations stakeholders during planning


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.