Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Project Management Professional (PMP) July 2026 Update PMP Question # 44 Topic 5 Discussion

PMI Project Management Professional (PMP) July 2026 Update PMP Question # 44 Topic 5 Discussion

PMP Exam Topic 5 Question 44 Discussion:
Question #: 44
Topic #: 5

A project manager is overseeing the development of a reporting system for a security trading company using an adaptive approach. During the development process,

a change in requirements is identified, necessitating the submission of a soft copy of the report to the regulator. The team suggests submitting the report manually to

avoid further delays.

What should the project manager do first?


A.

Ask the compliance team to review the regulation and categorize the requirement.


B.

Check with product owner for extra budget to outsource some of the work.


C.

Ask the project team to work overtime to have both requirements delivered on time.


D.

Discuss the priority and sequence of the work items with senior management.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.