Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 44 Topic 5 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 44 Topic 5 Discussion

PMP Exam Topic 5 Question 44 Discussion:
Question #: 44
Topic #: 5

A project to implement a new process is still in development. When implemented,

the company will benefit by a reduction in utility costs. The project financial evaluation

indicates a payback of 3 years.

What should the project manager do to expedite the project delivery?


A.

Increase resources on the technical design to enable a decision to proceed as this is aquick return project.


B.

Increase the time spent on project development to improve the level of confidence tovalidate the financial evaluation.


C.

Conduct a stakeholder survey with the plant operators to establish the probability ofthis project reducing the cost of utilities.


D.

Stop any further project development and commence with the implementation as thereis no need to seek further approval.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.