New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 44 Topic 5 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 44 Topic 5 Discussion

PMP Exam Topic 5 Question 44 Discussion:
Question #: 44
Topic #: 5

A project leader is preparing to facilitate a sprint retrospective. The sales manager sends the project leader an email asking how a feature planned for the next shipment is being implemented.

What should the project leader do next?


A.

Organize a meeting between the product owner and the sales manager.


B.

Invite the sales manager to the next sprint review.


C.

Organize a demo for the sales manager with the development team.


D.

Invite the sales manager to the sprint retrospective.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.