PMI Project Management Professional (2025 Version) PMP Question # 46 Topic 5 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 46 Topic 5 Discussion

PMP Exam Topic 5 Question 46 Discussion:
Question #: 46
Topic #: 5

During a status review meeting a team member raises concerns about tasks that are not being completed due to an underperforming resource on the team. What should the project manager do first?


A.

Ask the team to solve the issue internally and review the underperforming resource's situation


B.

Meet with the team member privately to discuss the problem and work together to find a solution


C.

Contact the functional manager and request to replace the team member with a better resource


D.

Discuss various options to improve the team member's performance with their functional managers


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.