PMI Project Management Professional (2025 Version) PMP Question # 46 Topic 5 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 46 Topic 5 Discussion

PMP Exam Topic 5 Question 46 Discussion:
Question #: 46
Topic #: 5

A company is about to start a complex research project. Due to the level of uncertainty, the project manager recommends the use of a hybrid approach; however, the organization only has experience with predictive projects.

How can the project manager strategize the use of a hybrid approach to the organization?


A.

Present the benefits of a hybrid approach to key stakeholders to get their support.


B.

Create a project change request to execute the project using a hybrid approach.


C.

Send a letter to the project management office (PMO) requesting to use a hybrid approach.


D.

Submit a notification to the project team confirming they will be using a hybrid approach on the project.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.