New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 46 Topic 5 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 46 Topic 5 Discussion

PMP Exam Topic 5 Question 46 Discussion:
Question #: 46
Topic #: 5

During the sprint planning of a project, the team members have a disagreement

about the comparative size of the backlog items and if they would fit into the next sprint.

Considering a hybrid approach, what should the project manager do?


A.

Ask an external technical leader to provide input and plan the sprint.


B.

Remove the items from the product backlog since the size couldn't be estimated.


C.

Make the decision about the backlog items based on what makes more sense.


D.

Facilitate the discussion so that the team members can reach a consensus.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.