Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Project Management Professional (PMP) July 2026 Update PMP Question # 46 Topic 5 Discussion

PMI Project Management Professional (PMP) July 2026 Update PMP Question # 46 Topic 5 Discussion

PMP Exam Topic 5 Question 46 Discussion:
Question #: 46
Topic #: 5

During a team ' s weekly status meeting, team members have minor disagreements about how to perform work and some defer to the team lead while others speak

confidently. The project manager realizes that team members have different expectations of the team ' s dynamics and operating model.

What should the project manager do?


A.

Create a team charter to define and document the expectations at the team level.


B.

Document the expectations based on a previous project and share these with the team.


C.

Ask the sponsor to document the team expectations and share these with the team.


D.

Create a team charter and ask the project sponsor to communicate the expectations.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.