Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 26 Topic 3 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 26 Topic 3 Discussion

PMP Exam Topic 3 Question 26 Discussion:
Question #: 26
Topic #: 3

An equipment vendor will implement a new production line for a client company. The year-long project will include 2- to 4-month long iterations; however, the client's project manager has no agile experience.

How should the project manager ensure that the client is effectively represented in the daily meetings?


A.

Recommend agile training programs that best suit the client project manager's schedule.


B.

Realign the project to a predictive approach to ensure optimal collaboration between the teams.


C.

Propose a session tor essential agile Knowledge transfer for the client team to align with the daily meeting goals


D.

Provide the client project manager with agile best practice documents and web resources.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.