PMI Project Management Professional (2025 Version) PMP Question # 26 Topic 3 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 26 Topic 3 Discussion

PMP Exam Topic 3 Question 26 Discussion:
Question #: 26
Topic #: 3

A project manager is managing a large project. During a review meeting, the project manager discovers that one of the team members who use to be a high performer was not able to complete their work on time.

What should the project manager do?


A.

Talk to the team member to determine why their performance changed.


B.

Talk to the team member and a human resources (HR) representative.


C.

Talk to the team member's manager to provide more training.


D.

Talk to the project lead and ask them to allocate less demanding tasks.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.