New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 26 Topic 3 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 26 Topic 3 Discussion

PMP Exam Topic 3 Question 26 Discussion:
Question #: 26
Topic #: 3

A project lead was asked to support the team by subdividing the project tasks as necessary to help define the minimum viable product (MVP).

Which two steps should the project lead take to define the MVP? (Choose 2)


A.

Hold a team meeting to generate a work breakdown structure (WBS).


B.

Create a responsible, accountable, consulted, informed (RACI) chart.


C.

Develop a project management plan, including subtasks, to meet the requirements.


D.

Conduct an information gathering session to determine the project value.


E.

Refer to the stakeholder register to determine who should be consulted.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.