Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Project Management Professional (PMP) July 2026 Update PMP Question # 26 Topic 3 Discussion

PMI Project Management Professional (PMP) July 2026 Update PMP Question # 26 Topic 3 Discussion

PMP Exam Topic 3 Question 26 Discussion:
Question #: 26
Topic #: 3

The project manager could not get the estimated initial budget for an infrastructure project, leaving the team uncertain about which part of the project should be

‘started. What should the project manager do?


A.

Use the budget defined by the organization and proceed according to the scope.


B.

Ask the sponsor if the project can be started without the budget defined.


C.

Start the work immediately with the given budget.


D.

Calculate a detailed budget to determine a solution.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.