PMP Exam Topic 3 Question 25 Discussion:
Question #: 25
Topic #: 3

During a project's execution phase, the team faced a setback in one of the deliveries and was asked to come up with a new plan. All team members joined a meeting to address the issue and, after a while, the project manager observed that two members of the team were just agreeing with anything that was proposed even though they were opposed to the outcome.

What conflict resolution style were the team members adopting?


A.

Avoidant style


B.

Combative style


C.

Collaborative style


D.

Accommodative style