A servant leader is about to start a confidential agile research project. A high risk has been identified related to a team member disclosing details of the project with external people.
What should the servant leader do to address this risk?
A.
Include this restriction as a ground rule and ensure all team members are familiar with it by reviewing the ground rules at the end of every
iteration.
B.
Forecast the cost of the risk to calculate the required contingency reserve that needs to be allocated if the risk materializes.
C.
Ask the functional manager to educate the team about this risk and ensure that disciplinary actions will be taken.
D.
Contact the human resources (HR) department to ensure that disciplinary actions will be taken if the employees disclose any confidential
In an agile project, the servant leader plays a crucial role in ensuring that the team understands and adheres to the project’s rules and guidelines. In this case, where there is a high risk of a team member disclosing confidential project details, the servant leader should include a restriction against such disclosure as a ground rule. This rule should be reviewed at the end of every iteration to ensure that all team members are familiar with it and understand its importance. This approach not only addresses the risk but also fosters a culture of trust and respect within the team. References: Project Management Professional (PMP) Reference Materials source and documents, Professional in Business Analysis Reference Materials study guide.