PMI Project Management Professional (2025 Version) PMP Question # 36 Topic 4 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 36 Topic 4 Discussion

PMP Exam Topic 4 Question 36 Discussion:
Question #: 36
Topic #: 4

A protect team member is having difficulty delivering assigned tasks for a project that is at risk of being delayed The main issue is that the team member does not understand a new system that was recently implemented

What should the project manager do?


A.

Ask the team member to learn the new system as on-the-job training


B.

Issue a change request to extend the project schedule


C.

Escalate the team members performance to the project sponsor


D.

Assign an experienced resource to support the team member


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.