Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Project Management Professional (PMP) July 2026 Update PMP Question # 36 Topic 4 Discussion

PMI Project Management Professional (PMP) July 2026 Update PMP Question # 36 Topic 4 Discussion

PMP Exam Topic 4 Question 36 Discussion:
Question #: 36
Topic #: 4

Acustomer has agreed in a contract that interactive displays will be delivered to 14 locations by the end of the year. The contract also states that only software

approved by the customer will be installed on these displays. The customer has not approved this new software because they lack the resources to test and approve

it.

What should the project manager do?


A.

Offer a phased delivery approach for the software.


B.

Assume the software will be approved by the client.


C.

Focus on meeting the delivery deadline.


D.

Escalate installation to the steering committee.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.