PMP Exam Topic 4 Question 35 Discussion:
Question #: 35
Topic #: 4

A team member regularly interrupts the virtual project status meeting with new recommendations. This action prevents other team members from providing their detailed status information.

What should the project manager do?


A.

Ask the individual to share the comments after the meeting for review.


B.

Include human resources (HR) to address the issue in the next meeting.


C.

Reinforce the importance of applying the team ' s ground rules to everyone.


D.

Encourage everyone to follow the ideas since the team member is senior.