PMI Project Management Professional (2025 Version) PMP Question # 34 Topic 4 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 34 Topic 4 Discussion

PMP Exam Topic 4 Question 34 Discussion:
Question #: 34
Topic #: 4

A project manager is assigned to a yearlong project. Before the start of the design phase, a competitor announces that they will release a similar deliverable in 8 months, although with fewer features and functionality.

Which two actions should the project manager take next? (Choose 2)


A.

Modify the project management plan with an incremental approach.


B.

Evaluate the impact of incremental deliverables.


C.

Reduce the scope items of the final deliverable.


D.

Discuss and review this external risk with the project sponsor.


E.

Update the project artifacts to include this issue.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.