PMI Project Management Professional (2025 Version) PMP Question # 28 Topic 3 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 28 Topic 3 Discussion

PMP Exam Topic 3 Question 28 Discussion:
Question #: 28
Topic #: 3

A sales team working on an IT deployment project approached the project manager on several occasions and complained about nonpayment of their overtime pay. The project manager realized that other team members are receiving their overtime pay

What should the project manager do next?


A.

Have a discussion with the sales team to find a solution to the issue


B.

Validate the reason and add n as an issue m the issue log


C.

Escalate the issue to the functional manager


D.

Direct the sales team to speak with accounting to resolve the issue


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.