Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Project Management Professional (PMP) July 2026 Update PMP Question # 28 Topic 3 Discussion

PMI Project Management Professional (PMP) July 2026 Update PMP Question # 28 Topic 3 Discussion

PMP Exam Topic 3 Question 28 Discussion:
Question #: 28
Topic #: 3

A project manager is leading a global project involving third-party contractors, internal stakeholders, and regulators. During a project board meeting, stakeholders are

informed of a regional compliance issue that could delay a critical milestone. One stakeholder demands immediate resolution, while another stakeholder thinks it is

not a priority.

What should the project manager do?


A.

Use the communications management plan to develop a message to stakeholders explaining the situation.


B.

Attempt to resolve the conflict within the project team to avoid unnecessary escalation.


C.

Escalate to the sponsor as it represents a serious compliance issue with implications for milestones.


D.

Escalate in accordance with the agreed escalation process to refer the issue to the appropriate deciding authority.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.