Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 31 Topic 4 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 31 Topic 4 Discussion

PMP Exam Topic 4 Question 31 Discussion:
Question #: 31
Topic #: 4

A project manager working on a large-scale network implementation is frustrated

with the hardware supplier. Their deliveries have been consistently late and frequently do not have vital components. The project manager's company has decided to cancel the contract and move to a new supplier, but the only other option is an overseas company.

What should the project manager do first to proceed with this change?


A.

Engage the services of an interpreter who understands the project domain.


B.

Check social media to determine if there are any common connections that use the new supplier.


C.

Request assistance from the procurement department on the next steps.


D.

Become aware of any cultural characteristics of the new supplier that could impactnegotiation.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.