Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Project Management Professional (PMP) July 2026 Update PMP Question # 31 Topic 4 Discussion

PMI Project Management Professional (PMP) July 2026 Update PMP Question # 31 Topic 4 Discussion

PMP Exam Topic 4 Question 31 Discussion:
Question #: 31
Topic #: 4

A project team is tasked with implementing a new technology system for the end users. The project team currently lacks information on what the system is used for

and how the end users would use it.

What should the project manager do?


A.

Request the project management office (PMO) if they can support with beneficial information.


B.

Hire external expert resources who have the knowledge about the system.


C.

Encourage the senior project resources to find out the purpose of the system.


D.

Ask the sponsor to define the project objectives and goals in the project documents.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.