PMI Project Management Professional (2025 Version) PMP Question # 31 Topic 4 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 31 Topic 4 Discussion

PMP Exam Topic 4 Question 31 Discussion:
Question #: 31
Topic #: 4

A product team is comprised of consultants and staff members Most of the team members agree on risks and the defined risk actions. One consultant discovers a new risk and communicates it directly to management.

What should the project manager do?


A.

Reject the risk because the team is not in agreement on escalating it


B.

Include the risk in the risk assessment and evaluate it with the team


C.

Accept the risk and immediately enter the risk into the risk register


D.

Discuss with the consultant to understand why the risk was escalated


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.