Question #: 30
Topic #: 4

A project team is using an iterative and incremental delivery approach. The sprint's duration is 1 month with a production release every 3 months. In the last sprint review, the users communicated that they want the functionality presented and deployed in 5 weeks. The project lead is working on the next release plan.

When should the project lead have their team deploy the functionality?


A.

In 1 month


B.

In 5 weeks


C.

In 12 weeks


D.

In 2 months