Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Project Management Professional (PMP) July 2026 Update PMP Question # 33 Topic 4 Discussion

PMI Project Management Professional (PMP) July 2026 Update PMP Question # 33 Topic 4 Discussion

PMP Exam Topic 4 Question 33 Discussion:
Question #: 33
Topic #: 4

A project manager works for a communications company. The manager of the mobile equipment department is concerned about the current project ' s activities.

According to the current project management plan, the department will need to purchase special equipment, but the cost was not planned. The project sponsor insists

the project should move forward because customers will be impacted if the equipment is not available.

What should the project manager do?


A.

Escalate the conflict to the project sponsor.


B.

Use the contingency reserve to fund the equipment cost.


C.

Resolve the issue in favor of the department manager to continue the project.


D.

Estimate the cost of purchasing the equipment and submit a change request.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.