New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 33 Topic 4 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 33 Topic 4 Discussion

PMP Exam Topic 4 Question 33 Discussion:
Question #: 33
Topic #: 4

A project is in the start-up phase of the project life cycle. The project team consists of 20 people from five different countries. The project team is scheduled to have quarterly face-to-face meetings. However, due to unforeseen circumstances, no face-to-face meetings can occur. The project manager is concerned that the team may not be able to fulfill their individual roles without face-to-face meetings.

What should the project manager do in this situation?


A.

Review the risk register for this unforeseen circumstance.


B.

Utilize virtual teams for meetings and deliverables.


C.

Use the contingency reserve and subcontract the work.


D.

Ask for an extension of time on the project deliverables.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.