PMI Project Management Professional (2025 Version) PMP Question # 33 Topic 4 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 33 Topic 4 Discussion

PMP Exam Topic 4 Question 33 Discussion:
Question #: 33
Topic #: 4

During a kick-off meeting at the start of project execution, the vendor presents a

migration plan to client stakeholders. The director of the business unit that owns the solution being migrated demands the ability to make the final go/no-go decision about whether the systems go live.

What should the project manager do?


A.

Schedule a meeting with the director to provide proof of expertise so the client

stakeholders will trust the project team's decision.


B.

Schedule a meeting with the project sponsor to determine if it is appropriate to accept

the director's request to provide a decision.


C.

Confirm with the director that the client stakeholders will be made accountable for the

decision in the responsibility assignment matrix (RAM).


D.

Ask the client to initiate a change request to make the director accountable for the

decision.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.