PMI Project Management Professional (2025 Version) PMP Question # 33 Topic 4 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 33 Topic 4 Discussion

PMP Exam Topic 4 Question 33 Discussion:
Question #: 33
Topic #: 4

A project team consists of several consultants from an external vendor. These consultants often change from month to month.

What should the project manager do to communicate the organizational values?


A.

Distribute the team charter to new team members.


B.

Host a question and answer (Q&A) session with the new team members.


C.

Schedule a collaborative team outing to strengthen team relationships.


D.

Review communications options with the vendor.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.