New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 29 Topic 3 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 29 Topic 3 Discussion

PMP Exam Topic 3 Question 29 Discussion:
Question #: 29
Topic #: 3

A team is using an agile approach to maintain the project backlog. A new project obstacle was identified as a blocker and added to the backlog list. The team is facing challenges to remove this obstacle.

What should the project manager do next?


A.

Escalate the obstacle to a servant leader for resolution.


B.

Make changes to reprioritize the backlog because of the obstacle.


C.

Reject the obstacle and present the partial solution to the customer.


D.

Focus on generating business value despite the obstacle.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.