Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 29 Topic 3 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 29 Topic 3 Discussion

PMP Exam Topic 3 Question 29 Discussion:
Question #: 29
Topic #: 3

A project has been running for 2 months and now requires approval for a supplier to

begin some execution tasks. The project team has evaluated several suppliers and selected

their top two preferred suppliers. The project sponsor requested that another supplier who has

lower costs be added to the list. However, the project manager is aware that this supplier

does not always fulfill the project requirements.

What should the project manager do?


A.

Set up a requirements review session and obtain agreement for selection criteria.


B.

Recommend to the team to add the sponsor's preferred supplier to the list.


C.

Choose the sponsor's preferred supplier for the project to avoid conflict between theteam and sponsor.


D.

Recommend to the sponsor to review the results of the team's supplier evaluation.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.