PMI Project Management Professional (2025 Version) PMP Question # 29 Topic 3 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 29 Topic 3 Discussion

PMP Exam Topic 3 Question 29 Discussion:
Question #: 29
Topic #: 3

A project manager noticed that the functional manager is not cooperating with staff assignment schedules and is always finding excuses not to release the requested staff. What should the project manager do first?


A.

Ask the leadership team for help obtaining the needed staff.


B.

Have a direct talk with the functional manager to understand the reasons behind their attitude.


C.

Evaluate the impact caused by the delay of forming the team and confront the functional manager.


D.

Check with human resources (HR) regarding the availability of staff.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.