Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Project Management Professional (PMP) July 2026 Update PMP Question # 29 Topic 3 Discussion

PMI Project Management Professional (PMP) July 2026 Update PMP Question # 29 Topic 3 Discussion

PMP Exam Topic 3 Question 29 Discussion:
Question #: 29
Topic #: 3

During a sprint review, the customer described a strong market trend that will highly impact the product vision and the project management plan. What should the

project manager do?


A.

Acknowledge the changed value proposition and request the team undo the scope of the last sprint.


B.

Interrupt the customer and underline the importance to stick to the approved documents.


C.

Review the customer ' s needs and define the backlog items according to the situation.


D.

Continue executing the project backlog as planned and introduce the changes in later stages.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.