PMI Project Management Professional (2025 Version) PMP Question # 1 Topic 1 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 1 Topic 1 Discussion

PMP Exam Topic 1 Question 1 Discussion:
Question #: 1
Topic #: 1

During the final iteration of the execution phase, the project has a cost performance

index (CP!) of 0.9 and a schedule performance index (SPI) of 1.0.

How should the project manager avoid a budget shortfall?


A.

Follow the risk management plan.


B.

Reduce the team effort utilization.


C.

Look for cost-saving opportunities.


D.

Submit a change request to add to the management reserve.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.