Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 1 Topic 1 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 1 Topic 1 Discussion

PMP Exam Topic 1 Question 1 Discussion:
Question #: 1
Topic #: 1

A project team is identifying project risks for a bridge to be built across a river. The team needs to send out invitations for a risk workshop to better understand the risks involved.

Which distribution list should the project manager use when sending out invitations?


A.

Functional managers, team members, and external consultants with experience in the field


B.

Team members, engineers, and weather experts


C.

Team members, consultants from outside the project with experience in the field, and the customer


D.

Weather experts, functional managers, and team members


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.