Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 1 Topic 1 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 1 Topic 1 Discussion

PMP Exam Topic 1 Question 1 Discussion:
Question #: 1
Topic #: 1

The project team completed a demonstration of the main deliverable of the project. Although the project sponsor is happy with the outcome and is ready to sign the release to production, one of the business unit managers who attended the demo believes that the deliverable is not complete.

Which document should the project manager use to resolve this situation?


A.

Requirements traceability matrix


B.

Risk management plan


C.

Project scope statement


D.

Requirements management plan


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.