PMI Project Management Professional (2025 Version) PMP Question # 1 Topic 1 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 1 Topic 1 Discussion

PMP Exam Topic 1 Question 1 Discussion:
Question #: 1
Topic #: 1

During a sprint retrospective, the project manager notices that one of the team members does not achieve the sprint objectives on a regular basis. This team member is an experienced resource.

How should the project manager properly address this situation?


A.

Align the project goals with the team member.


B.

Reassign the team member to another project.


C.

Nominate the team member to receive agile training.


D.

Allocate another resource to support the team member.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.