PMI Project Management Professional (2025 Version) PMP Question # 37 Topic 4 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 37 Topic 4 Discussion

PMP Exam Topic 4 Question 37 Discussion:
Question #: 37
Topic #: 4

A project has recently completed its production go-live, meeting the project's completion requirements in accordance with the scope document. However, the customer has been requesting a number of significant project enhancements.

How should the project manager address the customer's requests?


A.

Inform the customer that the project scope is completed and that further enhancements will require the initiation of a new project.


B.

Tell the client that any extra work will require new scoping and pricing before the team can start additional enhancements.


C.

Adjust the project completion requirements to the proposed enhancements and inform the project team of the additional work.


D.

Explain to the customer that the project has been completed and enhancements will follow the change management process.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.