PMI Project Management Professional (2025 Version) PMP Question # 37 Topic 4 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 37 Topic 4 Discussion

PMP Exam Topic 4 Question 37 Discussion:
Question #: 37
Topic #: 4

A company strictly uses an agile approach, and the backlogs are continuously updated. A new project lead is hired and feels uncomfortable sharing some of the product's vital information with the team and the product owner.

What does the project lead need to do to prevent a risky situation in the next iterations?


A.

Keep the project focused and executed in silos for better outcomes.


B.

Report the concern to the agile project management office (PMO),


C.

Inform the product owner of the concern so that i can be addressed.


D.

Open up to the team to work collaboratively to achieve the outcomes.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.