Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Project Management Professional (PMP) July 2026 Update PMP Question # 37 Topic 4 Discussion

PMI Project Management Professional (PMP) July 2026 Update PMP Question # 37 Topic 4 Discussion

PMP Exam Topic 4 Question 37 Discussion:
Question #: 37
Topic #: 4

A digital health development team is tasked with designing a new product, which is a pioneering effort for the organization and one of the few available in a

‘competitive market. The planning and auditing processes have been notably time-consuming. The development team has reported limited rework and minimal

customer complaints; however, the current budget significantly exceeds the typical project baselines for previous product development initiatives within the

organization. The project manager is currently analyzing the total cost of quality for the project.

What should the project manager do?


A.

Maintain the planned investment, appraisal, and prevention cost plan to reduce failure costs.


B.

Increase prevention costs to maintain project stability, reduce failure costs, and support the pace of change.


C.

Reduce internal costs to increase time to deliver value on schedule and on budget and reduce failure costs.


D.

Increase internal failure costs to detect defects early and minimize risks.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.