PMI Project Management Professional (PMBOK 7th Version) PMP Question # 37 Topic 4 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 37 Topic 4 Discussion

PMP Exam Topic 4 Question 37 Discussion:
Question #: 37
Topic #: 4

A project manager is working on a cost-reimbursable contract from the client's side. During project execution the project manager notices a major deliverable is missing. The project manager raises this with the seller but the seller advises the project manager that the subject deliverable is not part of the contract. The project manager remembers negotiating and agreeing to this deliverable during the tender process but cannot find it in the contract

What should the project manager do?


A.

Request a change in the contract in order to add the deliverable


B.

Add this deliverable to the requirements traceability matrix


C.

Terminate the contract and commence the closeout process


D.

Look to see if the deliverable is described in the statement of work (SOW)


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.