PMI Project Management Professional (2025 Version) PMP Question # 45 Topic 5 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 45 Topic 5 Discussion

PMP Exam Topic 5 Question 45 Discussion:
Question #: 45
Topic #: 5

A project manager has developed a communications management plan. A junior team member asks why they are duplicating efforts by producing different versions of the same newsletter.

How should the project manager respond?


A.

Explain that each stakeholder expects a different customized newsletter, ensuring it complies to all of their requirements.


B.

Explain that to prepare for all situations and as part of risk mitigation, many different newsletters are created just in case they are needed.


C.

Explain that customized newsletters are part of the organizational culture and that following this step-by-step process is of utmost importance.


D.

Explain that each individual newsletter is based on specific categories of communication for the intended audience.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.