PMP Exam Topic 5 Question 45 Discussion:
Question #: 45
Topic #: 5

An agile project is in its early iterations, but the project manager already realizes that

more resources will be needed to achieve the expected time lines. There are no internal

resources. available.

What vendor strategy should the project manager use to maximize project delivery?


A.

Use compression techniques to break down the scope and assign the scope pieces to

different vendors with a fixed-price contract.


B.

Use the contingency budget for hiring additional vendor resources to mitigate any project

risk.


C.

Engage in a time and materials (T&M) contract and hire a local vendor to support

development.


D.

Establish a solid view of the scope and requirements and engage a vendor with a fixed price contract.