Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Project Management Professional (PMP) July 2026 Update PMP Question # 45 Topic 5 Discussion

PMI Project Management Professional (PMP) July 2026 Update PMP Question # 45 Topic 5 Discussion

PMP Exam Topic 5 Question 45 Discussion:
Question #: 45
Topic #: 5

An agile team recently finished a product that met stakeholder expectations. However, a subsequent audit revealed that the product does not comply with local

regulations. The team lead learns the team focused on the functions of the product and not the regulatory issues.

What should the team lead do differently for the next project?


A.

Remind the project team that they should collect requirements from all stakeholders.


B.

Coach the team to solicit nonfunctional requirements in addition to functional requirements.


C.

Instruct the product owner to revise the definition of done (DoD) during the sprint review meeting.


D.

Conduct daily meetings to review the functional and nonfunctional requirements.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.