New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 45 Topic 5 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 45 Topic 5 Discussion

PMP Exam Topic 5 Question 45 Discussion:
Question #: 45
Topic #: 5

A project manager is overseeing a 10-mile piping installation project that was supposed to spend US$15,000 per mile of piping installation and should complete the project exactly 20 weeks from its start. The project manager just found out that only 80% of the work has been completed.

What is the budget at completion (BAC)?


A.

US$100,000


B.

US$150,000


C.

US$300,000


D.

US$250,000


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.