Question #: 10
Topic #: 2

A project is on schedule. However, during a site visit, a project manager notices that the contractor's productivity is low.

What should the project manager do?


A.

Assess the opportunity to deliver the project ahead of schedule and introduce a reward system.


B.

Discuss the need to increase productivity with the contractor.


C.

Plan the close-out activities since the project is on schedule.


D.

Update the project schedule to align with the contractor's productivity.