Question #: 10
Topic #: 2

A scrum master is leading an agile project to develop a video game product. Midway through a sprint, the customer asks the team to immediately add a new feature

to the product. The team asks the scrum master for guidance.

What should the scrum master do first?


A.

Add it to the product backlog.


B.

Negotiate increasing the sprint length.


C.

Estimate effort for the new feature.


D.

Add it to the current sprint.