Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 8 Topic 1 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 8 Topic 1 Discussion

PMP Exam Topic 1 Question 8 Discussion:
Question #: 8
Topic #: 1

A project manager has been given a critical, 5-day window and is allocated a maximum of US$100,000 as a contingency reserve. Subsequently, the project manager drafted

a course of action based upon the best available information. Overall, five actions were required to be completed at a cost of US$20,000 and a duration of 1 day each. After

3 days of work, the project manager completed two actions and spent US$80,000.

What should the project manager do next?


A.

As the CPI and SPI are greater than 1.0, reevaluate and prioritize the remaining actions.


B.

Stop the work and raise a project change request to the change control board (CCB) for additional funds and a project schedule extension.


C.

As the cost performance index (CPI) and schedule performance index (SPI) are less than 1.0, reevaluate and prioritize the remaining actions.


D.

Complete all actions and then inform the client of the additional cost and schedule overrun needed to complete the project.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.