PMI Project Management Professional (2025 Version) PMP Question # 8 Topic 1 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 8 Topic 1 Discussion

PMP Exam Topic 1 Question 8 Discussion:
Question #: 8
Topic #: 1

A project manager became aware of misunderstandings between a key stakeholder

and a team member with regard to some of the features defined in the project scope. What

should the project manager do?


A.

Reconcile the key stakeholder to the team member's recommendation.


B.

Reconcile the team member to the key stakeholder's recommendation.


C.

Escalate the communication concerns to the project management office (PMO) and

request that they take action


D.

Work with both the team member and the key stakeholder to reach a consensus.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.