PMI Project Management Professional (2025 Version) PMP Question # 8 Topic 1 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 8 Topic 1 Discussion

PMP Exam Topic 1 Question 8 Discussion:
Question #: 8
Topic #: 1

An adaptive project is in the planning stage. The project manager is preparing a communications management plan to share critical, project-related information and updates.

Which approach should the project manager take?


A.

Implement pull communication to share project-related information and updates.


B.

Install push communication to share project-related information and updates.


C.

Employ verbal techniques to share project-related information and updates.


D.

Apply information radiators to share project-related information and updates.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.